Supporting capability

Post-Weld Heat Treatment, DHT & De-magnetisation

In-house post-weld heat treatment, de-hydrogenation and de-magnetisation with recorded charts, as required by applicable codes and project specifications.

  • PWHT
  • De-hydrogenation (DHT)
  • Pre-heat & Inter-pass Control
  • De-magnetisation
  • Recorded Charts

Heat treatment and associated documentation as required by applicable codes and project specifications.

Alloy steels such as P11, P22 and P91 depend on correct pre-heat and post-weld heat treatment to reach their designed strength and toughness. SGE performs heat treatment in-house, with its own equipment and trained operators, so it is planned into every boiler, reformer, heater and piping job rather than added at the end. We regularly deliver 100% stress relieving on IBR jobs where specified, and every cycle is recorded and presented with the radiography and hardness results.

Detailed work scope

What we provide

  • Post-weld heat treatment (PWHT)Local resistance heating of pipe, tube and nozzle joints
  • Stress relieving of pressure-part repairs, with controlled heating and cooling rates and soak times
  • De-hydrogenation heat treatment (DHT)For thick or highly restrained welds
  • Pre-heat and inter-pass temperature control during welding of alloy steels
  • De-magnetisationRemoval of residual magnetism before welding to prevent arc blow
  • Time-temperature charts from calibrated recorders, for the job dossier

Execution methodology

How we execute the work

  1. 01

    Procedure

    Heat-treatment cycle taken from the WPS and the code — temperature, rate, soak time and thermocouple layout.

  2. 02

    Set-up

    Heating pads, insulation and thermocouples installed and checked; recorders calibrated.

  3. 03

    Cycle

    Heating, soak and controlled cooling recorded continuously.

  4. 04

    Verification

    Charts reviewed and hardness checked on alloy steels where specified.

Codes & standards

Work to the applicable codes and your specification

  • ASME B31.1 / B31.3 heat-treatment requirements
  • ASME Section VIII, as specified
  • Indian Boiler Regulations (IBR)
  • Project specifications and approved WPS

Materials we work with

  • P11 / P22 / P91
  • T11 / T22 / T91
  • Carbon steel
  • Low-alloy steel

Records you receive

Material certificates, WPS/PQR and welder qualifications, fit-up and weld records, PWHT charts, NDT and test reports — compiled into one indexed dossier.

Send us your requirement

Request a quote — PWHT / DHT

To prepare a realistic scope and schedule quickly, please share:

  1. Equipment or system details
  2. Drawings, datasheets or isometrics
  3. Plant location
  4. Planned shutdown or completion date

Attach drawings, datasheets or inspection reports to the form below (PDF, DWG, images, Excel or Word), or email them to info@sgeco.in.

We reply within one working day. See our privacy notice.

Have an industrial project or shutdown requirement?

Discuss your equipment replacement, repair, fabrication, erection or complete mechanical project requirements with our team.

Shree Ganesh Engineering Co.